ID | 活动名称 | IC | 活动工期(天)a | 工期变异系数 |
A | Perform prelim. mkt analysis | 0.5 | 8 | 0.8 |
B | Evaluate marketability options | 0.6 | 8 | 0.8 |
C | Engage feasibility consultants | 0.3 | 4 | 1.2 |
D | Evaluate planning & zoning process | 0.5 | 13 | 0.4 |
E | Perform massing study | 0.6 | 24 | 0.4 |
F | Develop conceptual design | 0.8 | 35 | 0.4 |
G | Identify external stakeholders | 0.4 | 8 | 0.8 |
H | Identify permits & approvals | 0.7 | 13 | 0.4 |
I | Complete Phase 1 ESA | 0.3 | 13 | 0.4 |
J | Evaluate consultants & contractors | 0.6 | 13 | 0.4 |
K | Obtain rough construction costs | 0.5 | 8 | 0.8 |
L | Determine highest & best use | 0.5 | 5 | 0.8 |
M | Identify debt options | 0.4 | 4 | 1.2 |
N | Identify equity options | 0.5 | 4 | 1.2 |
O | Update financial underwriting | 0.5 | 2 | 1.2 |
P | Reevaluate organization strategy | 0.6 | 3 | 1.2 |
Q | Estimate schedule | 0.6 | 4 | 0.8 |
R | Gain control of site and/or client | 0.6 | 4 | 1.2 |
S | Review and approve | 0.7 | 4 | 0.8 |