任务编号

紧前任务编号

关键资源占用量

自制成本/万元

自制周期/周

外协成本/万元

外协周期/周

R1

R2

R3

J 1

3

-

-

420

5

(670,770,800)

(4,3,2)

J 2

J 1

-

4

-

983

8

(1400,1300,1540)

(6,7,5)

J 3

3

-

-

2188

15

(2500,3000,3100)

(14,9,7)

J 4

J 3

-

-

4

815.7

6

(950,1000,1288)

(5,4,3)

J 5

J 3

-

2

-

1300

11

(1500,1700,1800)

(10,8,6)

J 6

4

-

-

950

7

(1000,1300,1400)

(6,5,3)

J 7

J 4

3

-

-

1856

10

(2000,2200,2300)

(7,4,3)

J 8

J 5

-

-

2

693.93

6

(830,900,1000)

(5,4,3)

J 9

J 6 , J 7

-

3

-

640.32

6

(680.34,700,800)

(5,4,3)

J 10

J 8 , J 15

1

-

-

1200.9

13

(1400,1500,1600)

(9,8,6)

J 11

-

3

-

777.35

7

(800,1000,1200)

(6,5,4)

J 12

-

4

-

1835.84

14

(2000,2300.34,2500)

(8,6,5)

J 13

J 10

-

-

5

969.87

10

(1100,1235.43,1300)

(8,7,6)

J 14

J 12 , J 16

3

-

-

500

6

(600.5,700.34,800)

(5,4,3)

J 15

-

2

-

930

7

(980,1200,1300)

(6,5,4)

J 16

J 11

-

-

4

967

8

(1000,1300,1500)

(7,6,5)