序号 | 工作内容 | RFI检查点 | 备注 |
1 | Paving Cutting (Carrier Pipe and FOC) | 0 |
|
2 | Excavation (Carrier Pipe) | 1 |
|
3 | Sand bedding and compaction (Min 200 mm) | 1 |
|
4 | Holiday Test, Pipe Lowering | 1 |
|
5 | Sand Backfilling and compaction (300 mm) | 1 | 压实度70% |
6 | CP installation/exothermic welding | 1 |
|
7 | Select Fill backfilling and Compaction (470 mm) | 1 | 压实度85% |
8 | Sub Base Preparation and Geogrid Installation (200 mm) | 1 | 压实度85% |
9 | Base Coarse Preparation (230 mm) | 1 | 压实度85% |
10 | MC-70 primer application | 1 |
|
11 | Binding coarse application |
| |
12 | RC-01 primer application | 1 |
|
13 | Wearing coarse application |
|