| PREPARATORY CHECKLIST (for start up) | |
| COATING | |
| 1 | ABRASIVE BLASTING SET UP - HOSE, AIR HOOD ETC. |
| 2 | AIR TANK RECEIVER (ASME STAMPED) APPROVED? |
| 3 | COMPRESSOR |
| 4 | AIR QUALITY TEST |
| 5 | BLOTTER TEST PAPER, AVAILABLE? |
| 6 | GRIT MATERIAL - AVAILABLE/INSPECTED-ACCEPTED? |
| 7 | PIPE BUNG |
| 8 | QC COATING- APPROVED? |
| 9 | COATING INSPECTION TOOLS (DEW POINT, DFT, PROFILE GAUGE, PRESSURE GAUGES, SURFACE TEMP. GAUDE, NEEDLE GAUGES) |
| 10 | HOLIDAY DETECTOR - EXTERNAL FBE COATING, AVAILABLE/CALIBRATED? |
| 11 | COATING APPLICATOR - ACS APPROVED JCC |
| 12 | COATING/BLASTER - SHAMS APPROVED JCC |
| 13 | CREW SUPERVISOR |
| 14 | ABRASIVE/COATING PROCEDURE (BY AHAK) - APPROVED? |
| 15 | EXT. COATING PROCEDURE- APPROVED |
| 16 | INT. COATING PROCEDURE- APPROVED |
| 17 | PAINT MATERIAL EXT- BY ACS |
| 18 | PAINT MATERIAL INT- BY ACS |
| 19 | CHORIDE TEST MATERIAL |
| 20 | ACS COATING CREW SUPV. AVAILABLE, APPROVED? |
| 21 | TOOLS FOR ABRADING EXISTING COATING |
| 22 | ABRAVISE CLEANING - JSA - APPROVED? |
| 23 | INTERNAL COATING - JSA- APPROVED? |
| 24 | EXTERNA COATING - JSA - APPROVED? |
| 25 | PAINT STORAGE CONTAINER - CONTRLLED TEMPERATURE WITH THEREMOMETER |
| 26 | PAINTING TRUCK - INSPECTED ok? - |